Containment Test of the First Unit at Akkuyu Nuclear Power Plant in Türkiye
Recently, the Akkuyu Nuclear Power Plant (Akkuyu NPP), constructed in Türkiye by the State Atomic Energy Corporation Rosatom of Russia, reached a key engineering milestone as the strength and tightness test of the sealed containment of the first unit's reactor building was successfully completed. The rigorous test, which lasted 8 consecutive days and nights, comprehensively verified the structural load-bearing capacity of the double-layer containment structure under extreme overpressure and negative pressure conditions, laying a solid foundation for the subsequent transition to hot and cold functional testing.

During this high-standard test, testing experts gradually raised the internal air pressure of the containment to 0.46 MPa, which is 15% higher than the calculated pressure used for conventional tightness assessment. At peak pressure, each square meter of surface bore a massive load equivalent to approximately 47 tonnes, after which the pressure was gradually and smoothly reduced. Meanwhile, the technical team conducted full-cycle real-time monitoring of the stresses generated in the structure and the changes in shape and dimensions under load through a high-precision monitoring system, and multiple core data confirmed that the protective barrier fully complies with stringent design specifications.
As a core safety feature of the Russian VVER-1200 Generation III+ reactor adopted at the Akkuyu NPP, the project employs an innovative double-layer containment design. The inner reinforced concrete containment, equipped with a steel tendon prestressing system, encloses the reactor main equipment and is lined with an internal steel liner, forming a robust barrier against the release of radioactive substances; while the outer reinforced concrete protective shell possesses outstanding capability to withstand extreme external combined hazards, including earthquakes of up to intensity 9, tsunamis, and hurricanes.
Sergey Butchikh, General Director of Akkuyu Nuclear JSC, stated that the control tests for the first unit are being steadily advanced as planned, and the successful completion of the containment strength test fully verified the overall construction quality. With this key protective barrier fully passing the test, the project is now ready to transition to hot and cold functional testing of the reactor facility in the near future, marking a decisive step by the Republic of Türkiye's first nuclear power plant toward final commercial power generation.
Disclaimer: Information republished from partner media, institutions or other websites is provided for reference and communication purposes only. It does not imply endorsement of its views or verification of its accuracy. Please contact us if any content infringes rights or requires correction.