Uzbekistan and Turkey to Strengthen Cooperation in the Field of Radiation and Nuclear Safety

Uzbekistan and Turkey to Strengthen Cooperation in the Field of Radiation and Nuclear Safety

Uzbekistan and Turkey reached an important agreement at the 70th General Conference of the International Atomic Energy Agency, aimed at strengthening cooperation between the two countries in the field of radiation and nuclear safety. The Scientific and Technical Center for Radiation and Nuclear Safety under the Committee for Industrial, Radiation and Nuclear Safety of Uzbekistan and the Turkish Nuclear Technical Support Joint Stock Company (NÜTED) signed the relevant documents, marking concrete steps forward in information exchange and technical collaboration between the two sides. The focus of cooperation lies in effectively utilizing their respective scientific and technological resources, sharing valuable experience, and applying modern safety methods in practical operations. Both sides recognize that in the field of nuclear safety, the exchange of experience and tech...

2026-09-18

Commissioning Preparation Work Begins for the Control System of Akkuyu NPP Unit 1 in Turkey

Commissioning Preparation Work Begins for the Control System of Akkuyu NPP Unit 1 in Turkey

The process automation control system of Akkuyu NPP Unit 1 in Turkey has begun preparations for pre-commissioning signal testing, which will be carried out before the physical start-up of the reactor. The process automation control system is the core hub of a nuclear power plant, enabling plant operating personnel to monitor and manage all process systems that support power generation. Akkuyu Nuclear Company noted in its announcement that the control systems used in the units of Akkuyu NPP possess the extremely high reliability characteristic of Russian-designed units. The control safety system responsible for automatic start-up and management of active safety systems has excellent fault tolerance, with a failure rate indicator reaching only one possible error per 1...

2026-09-18

Turkey and Danish Developer Sign Memorandum of Understanding on Thorium-Based Molten Salt Reactor Research

Turkey and Danish Developer Sign Memorandum of Understanding on Thorium-Based Molten Salt Reactor Research

On September 9, 2026, the Turkish Ministry of Energy stated that the Turkish Energy, Nuclear and Mining Research Institute (TENMAK) has signed a memorandum of understanding with Danish advanced reactor developer Copenhagen Atomics (CA), under which the two parties will conduct collaborative research on the application of thorium as a potential nuclear fuel for molten salt reactors. Tenmak and Copenhagen Atomics signed the memorandum of understanding on September 7. Photo courtesy of the Turkish Ministry of Energy and Natural Resources. The Turkish Ministry of Energy stated that the cooperation aims to advance research in areas related to thorium as a potential fuel for nuclear reactors, with a focus on assessing...

2026-09-10

Türkiye partners with Danish company to develop thorium-based nuclear technology

Türkiye partners with Danish company to develop thorium-based nuclear technology

Türkiye's Ministry of Energy and Natural Resources stated on September 7 that the Turkish Energy, Nuclear and Mineral Research Agency (TENMAK) has signed a memorandum of understanding with Danish nuclear technology developer Copenhagen Atomics to cooperate on developing next-generation nuclear energy technologies centered on Türkiye's thorium resources. According to the Turkish statement, the cooperation priorities include research and development of technologies that can utilize thorium, domestic production of thorium compounds in Türkiye, and promoting the participation of Turkish industrial enterprises, technology companies, and researchers in thorium-based nuclear technology development. The two sides will focus on thorium material preparation, research and development, and project design applicable to next-generation nuclear reactors, particularly molten salt reactors.

2026-09-08

Türkiye says Russia interested in participating in new nuclear power projects

Türkiye says Russia interested in participating in new nuclear power projects

Türkiye's Minister of Energy and Natural Resources Alparslan Bayraktar recently stated that Russia has expressed interest in participating in Türkiye's new nuclear power plant projects, including the Sinop nuclear power plant on the Black Sea coast and a nuclear power project in the northwestern Thrace region. South Korea, Canada, and China are also in contact with Türkiye regarding nuclear power cooperation. In an interview on September 6 local time, Bayraktar said Russia hopes to apply the experience and personnel accumulated during the construction of the Akkuyu nuclear power plant to the Sinop and Thrace nuclear power projects. He stated that in addition to Russia, Türkiye is also in contact with Canada...

2026-09-08

Türkiye continues negotiations with multiple countries on new nuclear power plants

Türkiye continues negotiations with multiple countries on new nuclear power plants

Turkish Minister of Energy and Natural Resources Alparslan Bayraktar stated that Türkiye's negotiations on new nuclear power plants have not yet been completed, and the country remains in contact with Russia, China, Canada, South Korea, and others, with no agreements signed for the relevant projects. Bayraktar said Russia is interested in participating in the Sinop and Thrace nuclear power plant projects and hopes to leverage the experience and human resources accumulated in the Akkuyu nuclear power plant project. In addition to Russia, Türkiye is also in negotiations with Canada, China, and South Korea on other nuclear power projects. He stated that beyond the Akkuyu plant, Türkiye plans to build eight more reactors...

2026-09-07

Turkey's Akkuyu Nuclear Power Plant Unit 1 to Generate Electricity by End of 2026

Turkey's Akkuyu Nuclear Power Plant Unit 1 to Generate Electricity by End of 2026

Turkish Energy Minister Alparslan Bayraktar stated that Unit 1 of the Akkuyu Nuclear Power Plant has entered the testing phase, with Turkey aiming to complete commissioning and begin electricity generation by the end of 2026. Bayraktar said construction of the remaining units at the Akkuyu Nuclear Power Plant is still progressing, and the project team also plans to build a data center near Units 3 and 4. He also noted that due to factors such as the pandemic, rising commodity prices, and increased construction costs, the total cost of the Akkuyu Nuclear Power Plant has exceeded the initially planned $20 billion. However, the project has made progress in localization, including equipment, materials, and services...

2026-09-07

Pre-commissioning WANO Peer Review Launched at Türkiye's Akkuyu Nuclear Power Plant

Pre-commissioning WANO Peer Review Launched at Türkiye's Akkuyu Nuclear Power Plant

The planning phase of the pre-commissioning peer review by the World Association of Nuclear Operators Moscow Centre (WANO-MC) has been launched at the Akkuyu Nuclear Power Plant (NPP) site in Türkiye. The plant, being constructed by Rosatom, is the first nuclear power plant under construction in Türkiye. This mission focuses primarily on Unit 1 of the Akkuyu NPP. Upon completion of the review, the World Association of Nuclear Operators (WANO) will conduct an independent assessment of the operational readiness of the unit's systems, equipment, and operating personnel, providing a reference for the subsequent safe operation of the unit. The review is led by Wang Tingkui, head of the WANO-MC Crew Performance Observation (CPO) and peer review team. According to...

2026-09-04

Putin Says Unit 1 of Turkey's Akkuyu Nuclear Power Plant Expected to Start in 2026

Putin Says Unit 1 of Turkey's Akkuyu Nuclear Power Plant Expected to Start in 2026

Russian President Vladimir Putin stated that he believes Rosatom can start Unit 1 of Turkey's Akkuyu Nuclear Power Plant as scheduled in 2026. According to relevant information, Putin arrived in Kyrgyzstan on August 31 to attend the Shanghai Cooperation Organization summit. On September 1, he held talks with Turkish President Recep Tayyip Erdogan. During the talks, the two sides mentioned cooperation in the energy sector, with the Akkuyu Nuclear Power Plant project being a key focus. Putin stated that the two countries' major joint projects are still progressing, including the well-known Akkuyu Nuclear Power Plant...

2026-09-02

Turkey's Akkuyu Nuclear Power Plant can meet up to 10% of the country's energy consumption once all four units are operational

Turkey's Akkuyu Nuclear Power Plant can meet up to 10% of the country's energy consumption once all four units are operational

Rosatom recently released a report stating that the Akkuyu Nuclear Power Plant it is constructing in Turkey can meet up to 10% of Turkey's energy consumption demand once all four units are fully operational. The report notes that nuclear power projects implemented by Rosatom overseas can support relevant countries in enhancing their energy independence. Taking the Akkuyu Nuclear Power Plant as an example, once all four units are in operation, Turkey will have the capacity to meet a considerable portion of its energy consumption through this project. The Akkuyu Nuclear Power Plant is Turkey's first nuclear power plant, constructed with the participation of Rosatom. According to information disclosed by the company, the aforementioned contribution will be realized after all four units...

2026-08-29

Welding of main circulation pipeline completed for Unit 2 of Turkey's Akkuyu NPP

Welding of main circulation pipeline completed for Unit 2 of Turkey's Akkuyu NPP

On August 27, welding of the main circulation pipeline was completed for Unit 2 of Turkey's Akkuyu Nuclear Power Plant. The pipeline connects the reactor, steam generators, and main circulation pumps, and is one of the key components forming the primary circuit system of the reactor facility. The welding work lasted 73 days and involved welding 32 pipe joints. Engineering technicians, welders, fitters, pipe cutters, non-destructive testing personnel, heat treatment personnel, and quality inspection personnel participated in the relevant operations. During construction, each process step proceeded according to the established technological workflow, and welded joints had to pass inspection before moving to the next stage. According to reports, all welded joints underwent high-temperature heat treatment to relieve internal stress in the metal and ensure compliance with design performance requirements.

2026-08-28

Test vacuum established in turbine condenser of Unit 1 at Turkey's Akkuyu NPP

Test vacuum established in turbine condenser of Unit 1 at Turkey's Akkuyu NPP

On August 25, test vacuum was established in the turbine condenser of Unit 1 at Turkey's Akkuyu Nuclear Power Plant. This operation verified the readiness of the main systems of the turbine unit, creating conditions for subsequent commissioning work. Specialists from TITAN-2 Holding (TITAN-2) established the required vacuum in the condenser and checked the tightness of the vacuum system as well as the thermal and mechanical condition of the turbine. During the test, technical personnel continuously monitored key parameters such as steam pressure, bearing temperatures, thermal expansion of cylinders and rotors, and condenser vacuum level. While the turbine was rotated by the turning gear, experts also verified the operational condition of the turbine flow path. This...

2026-08-27

West Engineering Delivers 30 Relay Protection and Automation Cabinets for Unit 2 of Akkuyu NPP

West Engineering Delivers 30 Relay Protection and Automation Cabinets for Unit 2 of Akkuyu NPP

West Engineering has completed the next stage of equipment delivery for Unit 2 of the Akkuyu Nuclear Power Plant in Türkiye, shipping 30 relay protection and automation cabinets to the project site. The equipment will be used for the protection, monitoring, and control of critical electrical components of the power unit. The delivered equipment includes AZ-PZ cabinets for generating analog and discrete information, power supply unit protection device cabinets, power unit measurement device cabinets, synchronizing relay cabinets, generator switch control cabinets, electrical process recording cabinets, and control current distribution cabinets, among others. According to reports, this batch of nuclear facility equipment has been designed with high safety margins and fault tolerance in mind. The supplied relay protection and automation systems comply with relevant international standards, with a safety class of 3H/N, meeting the NP-001-15 standard; the quality assurance category is QA3, and the equipment has undergone multi-stage quality control from material and component selection to acceptance testing.

2026-08-20

Akkuyu NPP Unit 2 Completes Installation of Four Main Pump Sets

Akkuyu NPP Unit 2 Completes Installation of Four Main Pump Sets

The four main pump sets of the technical water supply system at the onshore pumping station of Unit 2 at Turkey's Akkuyu Nuclear Power Plant have been installed. Specialists from TITAN-2 Holding completed the installation, marking new progress in the construction of the turbine island cooling system for this unit. These large centrifugal pumps will be used to deliver seawater to the condenser cooling system of the turbine units. Once the unit is in operation, the continuous and stable operation of the pump sets will directly affect the cooling efficiency of the turbine hall equipment and influence the operational stability of the turbine units. According to reports, these pump sets are among the larger pump equipment at the nuclear power plant, with each pump standing as tall as a five-story building. The equipment is arranged in a tiered layout, with the pump bodies...

2026-08-19

Akkuyu Nuclear Power Plant: Türkiye's Gateway to the Nuclear Supply Chain and a Platform for Long-Term Technology Acquisition

Akkuyu Nuclear Power Plant: Türkiye's Gateway to the Nuclear Supply Chain and a Platform for Long-Term Technology Acquisition

On August 15, Professor Şer Ergun, Head of the Nuclear Engineering Department at Hacettepe University, commented on the commissioning progress of the Akkuyu Nuclear Power Plant in Mersin Province, emphasizing the project's strategic and technical significance for Türkiye. She noted that the VVER-1200 technology used at Akkuyu is operational in multiple countries worldwide, and Türkiye is seizing this opportunity to operate modern reactor technology while accumulating nuclear knowledge and experience and strengthening international cooperation through collaboration with other VVER-1200 user countries. She also stressed that Turkish engineers should actively participate in similar projects. Ergun stated that Akkuyu's value should not be assessed solely from the perspective of power generation, but also from its contribution to the nuclear technology ecosystem. The project provides...

2026-08-16

First unit of Türkiye's Akkuyu Nuclear Power Plant expected to generate power within months

First unit of Türkiye's Akkuyu Nuclear Power Plant expected to generate power within months

Turkish Energy Minister Alparslan Bayraktar stated on August 13 at the Bosphorus Diplomatic Forum held in Istanbul that the first reactor at Türkiye's Akkuyu Nuclear Power Plant is expected to begin generating electricity within the coming months. Bayraktar said that four reactors are currently being constructed simultaneously at the Akkuyu Nuclear Power Plant, and Türkiye hopes to achieve power generation from the plant's first unit in the coming months. He noted that developing nuclear power has been a long-term goal for Türkiye, and the Akkuyu project will bring Türkiye into the ranks of countries utilizing nuclear energy. Previously, Bayraktar had stated that Türkiye plans to launch the first power unit of the Akkuyu Nuclear Power Plant by the end of this year...

2026-08-14

Türkiye Maps Out Small Modular Reactors, Targeting 5,000 MW Installed Capacity by 2050

Türkiye Maps Out Small Modular Reactors, Targeting 5,000 MW Installed Capacity by 2050

Türkiye is positioning small modular reactors (SMRs) as a new breakthrough in its nuclear energy strategy. Under relevant plans, Türkiye aims to achieve approximately 5,000 MW of SMR installed capacity by 2050, a scale that would surpass the Akkuyu Nuclear Power Plant project. For Türkiye, which has long sought to reduce its external energy dependence, SMRs are seen as a strategic opportunity combining energy security, industrial upgrading, and technological competitiveness. Compared with traditional large-scale nuclear power plants, SMRs feature smaller installed capacity and more flexible deployment, typically ranging from 10 MW to 300 MW; micro modular reactors below 10 MW are even smaller and can be transported by truck. Reports note that such reactors can be deployed in...

2026-08-13

Akkuyu Nuclear Power Plant Launches Environmental Monitoring System, Recording Ecological Data to Build a

Akkuyu Nuclear Power Plant Launches Environmental Monitoring System, Recording Ecological Data to Build a "Digital Memory"

On August 10, the Akkuyu Nuclear Power Plant under construction in Mersin Province announced that its deployed high-tech environmental monitoring system has been put into operation, which will digitally record and track ecological environment changes around the plant site. The operator stated that the system not only serves the plant's own environmental compliance but also sets a new standard for environmental management in Türkiye. In terms of marine ecological monitoring, the modern chemical analysis laboratory activated on site is monitoring seawater quality in real time, regularly measuring multiple parameters such as water temperature, salinity, dissolved oxygen levels, and fish diversity. Through these data, the plant's impact on the marine ecosystem will be transparently documented. Particularly noteworthy...

2026-08-12

The Mecca Mutual Defense Agreement Opens a

The Mecca Mutual Defense Agreement Opens a "Finance-Industry-Nuclear" Triad, with Nuclear Energy as an Energy Security Sub-route among Six Economic Pathways

On August 7, Saudi Arabia, Turkey, and Pakistan signed the Mutual Defense Agreement in Mecca, attended by Saudi Crown Prince Mohammed bin Salman, Turkish President Erdogan, and Pakistani Prime Minister Shehbaz Sharif. The agreement binds Saudi financial weight + Turkish defense industry and manufacturing base + Pakistani nuclear and military experience into a single framework for the first time, stipulating that an armed attack on any one country is considered an attack on all, and covers joint defense industry, technology exchange, and training planning coordination. Saudi officials clarified that the agreement does not point to a military axis, religious bloc, or nuclear arms race, but rather to building self-sustaining capabilities. The New Arab, citing IISS, Chatham House, and Reuters/AP analyses...

2026-08-10

Installation of Passive Heat Removal System Completed for Unit 1 of Turkey's Akkuyu Nuclear Power Plant

Installation of Passive Heat Removal System Completed for Unit 1 of Turkey's Akkuyu Nuclear Power Plant

Rosatom recently announced that the installation of the Passive Heat Removal System (PHRS) for Unit 1 of Turkey's Akkuyu Nuclear Power Plant has been completed. This means the unit is now equipped with a critical safety system and is ready for the commissioning phase. According to reports, the installed equipment includes approximately 90 components such as heat exchangers, guide vanes, air ducts, and electromagnetic devices, which were installed in stages in the reactor building dome area. The Passive Heat Removal System is one of the key safety systems of a nuclear power unit, designed to remove residual heat from the reactor core under specific operating conditions. The system consists of four independent channels, each corresponding to one steam generator...

2026-08-10

Vacuum test of the turbine condenser at Unit 1 of Akkuyu NPP successfully completed

Vacuum test of the turbine condenser at Unit 1 of Akkuyu NPP successfully completed

The vacuum test of the turbine condenser at Unit 1 of Turkey's Akkuyu NPP, built by Rosatom, has been completed. The operation confirmed that the main systems of the turbine unit are ready for the next stage of commissioning. During the test, technicians established the required negative pressure in the condenser, checked the tightness of the vacuum system and the thermomechanical condition of the turbine, while monitoring parameters such as condenser vacuum, steam pressure, bearing temperatures, and thermal expansion of the casing and rotor. During the turning gear rotation of the turbine, the proper operation of the flow path (blades) was confirmed. Systems involved in the operation included: start-up boiler house boilers, vacuum system, bearing lubrication system, hydraulic jacking oil system, main turning gear, steam supply and extraction systems, as well as the equipment thermomechanical condition monitoring system.

2026-08-08