Ontario Power Generation Advances Darlington SMR Budget Update
Recently, Nicolle Butcher, President and CEO of Ontario Power Generation (OPG), announced that as the first commercial Small Modular Reactor (SMR) project in the Group of Seven (G7), construction of the first unit at Canada's Darlington nuclear site is facing engineering pressures. Affected by the ongoing complexity of first-of-a-kind engineering design and supply chain performance, the project will not be able to achieve commercial operation by the originally planned October 2030, nor will it be completed within the original budget.

Ontario Power Generation noted that the core cause of the cost and schedule pressures stems from the ongoing engineering design work on the BWRX-300 small modular reactor technology by technology provider GE Vernova Hitachi Nuclear Energy (GEVH) of the United States. Nevertheless, physical construction at the Darlington nuclear site continues to advance steadily, with the basemat installation for Unit 1 successfully completed earlier this year, and construction of the reactor and turbine buildings continuing to move forward.
To properly manage project risks and establish a robust response plan, Ontario Power Generation is working closely with the technology provider to comprehensively assess uncertainties in engineering design maturity, supply chain, and construction execution, and to further strengthen oversight of on-site construction and supply chain activities. Ontario Power Generation expects that a comprehensive assessment report covering the fully revised cost budget and construction schedule will be substantially completed by mid-2027, at which time more detailed information will be disclosed to the public and regulators.
Affected by the project's budget and schedule adjustments, the Ontario Energy Board has ordered the relevant parties to resume settlement negotiations on electricity rates and the project regulatory framework. Despite the inevitable challenges and difficulties of first-of-a-kind construction, Ontario Power Generation emphasizes that developing advanced small modular reactors remains of irreplaceable core strategic significance for meeting Ontario, Canada's growing demand for clean, reliable electricity in the future.
Disclaimer: Information republished from partner media, institutions or other websites is provided for reference and communication purposes only. It does not imply endorsement of its views or verification of its accuracy. Please contact us if any content infringes rights or requires correction.