Brazilian nuclear industry company starts fuel production for Angra 2's 22nd refueling
Brazilian Nuclear Industries (INB) has started production of nuclear fuel required for the 22nd refueling of Unit 2 at the Angra Nuclear Power Plant (Angra 2). On July 28, INB completed the assembly of the first fuel assembly at the Nuclear Fuel Factory (FCN) in Resende, Rio de Janeiro State; on July 30, the fuel assembly passed all established quality inspections in the production process and was certified. According to the plan, INB will manufacture a total of 52 fuel assemblies for this refueling. The assembly work is expected to be completed in December 2026 and delivered to Eletronuclear in March 2027. Recently, INB has made progress in several key stages of the nuclear fuel manufacturing chain. On July 28, approximately 240 tons of enriched...