Search Results

Keyword:nuclear power construction

U.S. Nuclear Power Construction Included as Candidate in South Korea's U.S. Investment Consultations

U.S. Nuclear Power Construction Included as Candidate in South Korea's U.S. Investment Consultations

On September 10, 2026, consultations between South Korea and the United States over a $350 billion U.S. investment plan entered a late stage. In addition to the Encinar gas combined-cycle power project in Texas being regarded as the first investment candidate, the U.S. side is said to have also proposed using a considerable portion of the $200 billion in strategic investment for nuclear power plant construction. According to related information, the U.S. nuclear power construction plan includes up to eight large nuclear reactors, and South Korea's APR1400 reactor design has also been included in discussions for some projects. South Korea's Ministry of Trade, Industry and Energy said regarding the nuclear power projects that relevant parties are in consultations, but specific details have not yet been determined. Texas's rapidly growing electricity demand is an important background for the South Korea-U.S. discussions on...

2026-09-10

Russia Says It Is Advancing Construction of Small Nuclear Power Plants

Russia Says It Is Advancing Construction of Small Nuclear Power Plants

Russian President Vladimir Putin stated at the plenary session of the Eastern Economic Forum (EEF) that Russia holds a unique position in the construction of small nuclear power plants, with related projects not merely in the planning and discussion stage but already entering actual construction. Putin said at the meeting that Russia is the only country in the world that is not only discussing the necessity and feasibility of developing small-scale nuclear power but is also taking action to build it. He noted that currently, no other country besides Russia has undertaken similar construction. ...

2026-09-04

World's First 250,000 Tonne-Meter Ring Crane Rolls Off Production Line, Supporting Hualong One 2.0 Nuclear Power Construction

World's First 250,000 Tonne-Meter Ring Crane Rolls Off Production Line, Supporting Hualong One 2.0 Nuclear Power Construction

On August 31, the world's first 250,000 tonne-meter ring crane, jointly developed by SANY Heavy Lift and China Energy Engineering Group Guangdong Thermal Power & Litte Company, rolled off the production line at SANY's Huzhou Industrial Park in Zhejiang. Designed for the "one crane, two islands" construction requirements of Hualong One 2.0, the equipment can address the engineering challenge of covering module hoisting for two nuclear islands with a single unit, marking a key domestic localization breakthrough in China's ultra-large-tonnage nuclear power hoisting equipment. With the advancement of the Hualong One 2.0 "one crane, two islands" construction method, nuclear power projects have imposed higher requirements on the working radius, load capacity, and hoisting precision of heavy lifting equipment. In the past, related high-end equipment technology was long controlled by a few overseas companies. The 250,000 tonne-meter ring crane rolled off the production line this time has undergone seven years of technical research, achieving breakthroughs in structural design, manufacturing processes, and assembly control.

2026-09-02

Northeast Regional Office of the Ministry of Ecology and Environment Conducts Construction Quality Dialogue for Xudabao Nuclear Power Plant

Northeast Regional Office of the Ministry of Ecology and Environment Conducts Construction Quality Dialogue for Xudabao Nuclear Power Plant

Recently, the Northeast Regional Office of Nuclear and Radiation Safety Supervision of the Ministry of Ecology and Environment (hereinafter referred to as the Northeast Office) held a construction quality dialogue with CNNC Liaoning Nuclear Power Co., Ltd. (hereinafter referred to as the Operating Unit) for the Xudabao Nuclear Power Plant, aiming to promote the implementation of nuclear safety responsibilities and ensure the effective operation of the quality assurance system. China National Nuclear Power Co., Ltd. and relevant construction participating units attended the event. The dialogue reviewed the Operating Unit's presentation on quality issues related to nuclear safety-related structures, systems, equipment, and design, systematically identified management shortcomings, analyzed root causes, and developed improvement measures. The Northeast Office pointed out that construction quality issues reflect that various units still have inadequacies in fulfilling nuclear safety responsibilities and quality assurance responsibilities, with insufficiently effective transmission of responsibility pressure. All units must deeply recognize that the Xudabao Nuclear Power Plant is at a critical stage with two reactor types and four units under simultaneous construction, where civil construction, installation, and commissioning tasks overlap, marking a high-risk period for construction quality. The primary nuclear safety responsibility of the Operating Unit must be firmly consolidated, and the corresponding nuclear safety responsibilities of all units must be reinforced.

2026-08-24

UK report calls for rebuilding nuclear power construction capability on time and on budget

UK report calls for rebuilding nuclear power construction capability on time and on budget

The UK think tank Onward recently released a report stating that if the UK hopes to achieve affordable electricity supply and drive deep decarbonization of its energy system, it must rebuild its capability to deliver nuclear power projects on time and on budget. The report, titled "Solid Foundations: The Case for Cheap, Reliable Power," proposes that the UK should adjust its renewable-dominated power system planning and build a diversified electricity mix comprising nuclear power, renewables, and gas generation, enabling consumers to access affordable electricity when needed. The UK Nuclear Industry Association (NIA) welcomed the report, noting that the issues it raises are of practical relevance. The report recognizes...

2026-08-23

Rosatom Continues Construction of New Units at Iran's Bushehr Nuclear Power Plant

Rosatom Continues Construction of New Units at Iran's Bushehr Nuclear Power Plant

Rosatom Director General Alexey Likhachev stated that the state atomic energy corporation is continuing construction of new units at Iran's nuclear power plant. In his address to nuclear industry workers and retirees on the occasion of the 81st anniversary of the Russian nuclear industry, Likhachev said that Rosatom is still building nuclear power plants in Egypt, Hungary, Iran, and India, while also launching new construction projects in Uzbekistan and Kazakhstan. According to relevant information, the second and third units of Iran's Bushehr Nuclear Power Plant are being built with Rosatom's participation. The Bushehr plant is one of Iran's key nuclear power projects, and the construction of new units is...

2026-08-21

Acceptance Inspection Completed for Auxiliary Pump Equipment at Egypt's El Dabaa Nuclear Power Plant

Acceptance Inspection Completed for Auxiliary Pump Equipment at Egypt's El Dabaa Nuclear Power Plant

A milestone in equipment quality control has been achieved at the construction project of the El Dabaa Nuclear Power Plant, Egypt's first nuclear power station. Recently, SpetsAtomResurs LLC, a Russian limited liability company, completed acceptance testing and final acceptance inspection of six auxiliary pump units at its production facility in Moscow, with the relevant equipment having passed pre-delivery quality confirmation. This quality control work was carried out from June 18 to July 21, 2026, fulfilling the supply obligations of SpetsAtomResurs LLC under the agreement concluded with JSC Atomstroyexport, the general contractor for the nuclear power plant construction. The equipment manufacturing and verification work was carried out in accordance with the established quality plan.

2026-08-19

Rosatom Plans to Send Additional Experts to Iran's Bushehr Nuclear Power Plant in September

Rosatom Plans to Send Additional Experts to Iran's Bushehr Nuclear Power Plant in September

Alexey Likhachev, CEO of Rosatom, said on August 18 that the company plans to send dozens of additional experts to Iran's Bushehr Nuclear Power Plant in September. At that time, the total number of Rosatom staff on site at the nuclear power plant will exceed 100. Likhachev stated that the company plans to dispatch several dozen more personnel in September, bringing its on-site workforce at the Bushehr plant to nearly 100. He also noted that this does not mean the project has fully resumed construction, but it will create conditions for the continued construction of the project and avoid work stoppages. According to reports, the Russian experts currently working at the Bushehr Nuclear Power Plant...

2026-08-19

First Power Transmission Line Commissioned at Smolensk NPP-2 Construction Site

First Power Transmission Line Commissioned at Smolensk NPP-2 Construction Site

The first power transmission line has been commissioned at the construction site of Russia's Smolensk NPP-2. The line will provide stable power supply and round-the-clock lighting for the construction and installation base, freeing on-site work from natural daylight constraints. According to the project schedule, the construction site is currently connected to the 10 kV grid via a temporary scheme, with a switch to the permanent power supply system planned after the 110/10 kV permanent substation is put into operation. During construction, the contractor laid over 3 kilometers of cable and installed more than 60 transmission line towers under challenging weather conditions. During the construction phase of the installation base, stable power supply plays a fundamental role in project progress. The site needs to complete the construction of rebar module and rebar cage fabrication workshops on schedule, establishing a complete preparation flow from metal processing to finished component delivery. These components will be used directly in the subsequent construction of the main structures of the nuclear power units.

2026-08-18

Vietnam Electricity Advances Preparatory Work for Ninh Thuan 1 Nuclear Power Plant

Vietnam Electricity Advances Preparatory Work for Ninh Thuan 1 Nuclear Power Plant

Vietnam Electricity (EVN) is advancing preparatory work for the Ninh Thuan 1 Nuclear Power Plant project, focusing on supporting measures in legal framework, financial arrangements, project management, human resource development, and public communication. The project is regarded as Vietnam's first nuclear power plant project and holds significant importance for ensuring energy security, promoting energy structure transition, and reducing carbon emissions. During the 7th National Nuclear Regulatory Conference, EVN Deputy General Director Nguyen Thai Anh stated that the Ninh Thuan 1 Nuclear Power Plant project must meet the highest technical, engineering, and safety requirements currently applicable in Vietnam. In the preparatory phase, EVN is focusing on addressing three categories of challenges while simultaneously advancing five groups of solutions to ensure the project proceeds in accordance with...

2026-08-17

Morocco Conducts 18 Expert Missions with IAEA in 2025, Civil Nuclear Cooperation Expands to African Level

Morocco Conducts 18 Expert Missions with IAEA in 2025, Civil Nuclear Cooperation Expands to African Level

Morocco's cooperation with the International Atomic Energy Agency is shifting from mere technical assistance to more active participation in regional capacity building. In 2025, Moroccan experts completed 18 international expert missions under the IAEA Technical Cooperation framework, with the agency's assistance to Morocco reaching €1.17 million in the same year. This indicates that Morocco has established a certain foundation in nuclear science, nuclear technology applications, and regulatory capabilities, and is beginning to play a more significant role in Africa's nuclear technology cooperation network. The National Center for Energy, Nuclear Science and Nuclear Technology in Rabat was granted the status of IAEA Collaborating Centre in September 2024, with a cooperation cycle covering 2025 to...

2026-08-15

Indian Government Approves INR 133.55 Billion Equity Funding for 6 Nuclear Power Projects Under Construction

Indian Government Approves INR 133.55 Billion Equity Funding for 6 Nuclear Power Projects Under Construction

To advance nuclear power construction and meet growing electricity demand, the Indian central government has approved equity funding of INR 133.55 billion (approximately RMB 13.355 billion) for six nuclear power projects under construction, with all funds fully disbursed. This information was disclosed by Dr. Jitendra Singh, Minister of State for Atomic Energy, in a written reply to the Rajya Sabha. Singh noted that multiple technical, supply chain, and global situation factors have caused project delays: significant design modifications required under new safety standards following the Fukushima nuclear accident in Japan; delays in supply of critical equipment; and the impact of the COVID-19 pandemic on construction progress. In addition, disrupted equipment supplies from Russia, financial difficulties faced by contractors after the pandemic, complex geological conditions, and a shortage of skilled workers have also slowed project momentum. The Russia-Ukraine conflict and ongoing geopolitical tensions in West Asia have further affected supply chains.

2026-08-14

Polish President Signs Key Nuclear Power Bill, Allowing Early Construction Works to Start Ahead of Schedule

Polish President Signs Key Nuclear Power Bill, Allowing Early Construction Works to Start Ahead of Schedule

Polish President Karol Nawrocki signed an amendment to the Act on the Preparation and Implementation of Nuclear Energy Facilities and Associated Investments on August 14, aiming to accelerate the construction of nuclear power plants in the country. According to information released by the Presidential Chancellery, the core of this legal adjustment is to allow certain preliminary construction and preparation works to proceed before the final construction permit for the entire project is granted, thereby shortening the timeline for large-scale nuclear projects. The amendment concerns Polish laws related to the preparation and implementation of nuclear energy facilities and associated investments. The new regulations introduce a new type of permit, namely the permit for preliminary construction works of nuclear energy facilities. Once this permit is obtained, the investor can carry out some early-stage construction and preparation works before all complete project investment documents have been fully approved.

2026-08-14

Hinkley Point C Nuclear Power Station Advances CCNSG Safety Passport Collaboration to Ensure Site Safety During Peak Construction

Hinkley Point C Nuclear Power Station Advances CCNSG Safety Passport Collaboration to Ensure Site Safety During Peak Construction

Hinkley Point C (HPC) nuclear power station in the UK is deepening its collaboration with the Client Contractor National Safety Group (CCNSG) to safeguard thousands of workers on site during the peak construction phase. Located in Somerset, the project is progressively transitioning from civil works to mechanical and electrical installation, placing greater demands on unified safety access standards and workforce competency. The CCNSG Safety Passport scheme, delivered by the Engineering Construction Industry Training Board (ECITB), has been operating in the engineering construction industry for over 30 years, with more than 85,500 active cardholders. The scheme is industry-led and continuously overseen by a relevant committee, of which Hinkley Point C is a member.

2026-08-13

Rosatom Resumes Sending Specialists to Bushehr Nuclear Power Plant

Rosatom Resumes Sending Specialists to Bushehr Nuclear Power Plant

Alexey Likhachev, Director General of Rosatom, stated on August 9 that the company has resumed sending specialists to the construction site of Iran's Bushehr Nuclear Power Plant, with the first batch of five engineering and technical personnel having arrived at the site and begun work. Likhachev said that with this batch in place, the total number of Russian specialists at the Bushehr project site has now increased to 25. The company plans to dispatch the next batch, numbering several dozen people, within the next two weeks, provided that the conflict between the United States and Iran does not escalate further. He indicated that under current arrangements, Rosatom plans to increase the number of personnel at the project site to 100 this autumn...

2026-08-10