Construction Site Leveling and Excavation Kicks Off for Hualong One Version 2.0 Demonstration Project of Zhejiang Jinqimen Nuclear Power Phase II
On the morning of September 9, Zhejiang Jinqimen Nuclear Power held a mobilization meeting for high-quality construction of the Hualong One Version 2.0 demonstration project of Phase II, marking the full launch of site leveling and excavation work for Phase II. At the event, Yao Zhaohong, General Manager of Jinqimen Nuclear Power, presented the flag to the Party Member Commando Team for High-Quality Commencement of the Demonstration Project. Zhong Hua, Party Secretary and Chairman of Jinqimen Nuclear Power, delivered a mobilization speech and announced the start of site leveling and excavation work. At 11:11, the first blast for the main excavation of Phase II was successfully detonated, marking that the project construction has entered a stage of accelerated advancement. The mobilization meeting stated that Jinqimen Nuclear Power undertakes the task of constructing the Hualong One Version 2.0 demonstration project, and all participating units and builders must fulfill safety and quality responsibilities, adhere to safety first and quality first, steadily advance project construction, and build a high-standard "New Quality Hualong Demonstration Project."
2026-09-10

First Application and Verification of Intelligent Monitoring and Adjustment System for Nuclear Power Plant Personnel Status at "Hualong One" Nuclear Power Plant
On September 4, CGN Engineering, in collaboration with Cangnan Nuclear Power, successfully completed the testing, verification, and on-site data collection of the Intelligent Monitoring and Adjustment System for Nuclear Power Plant Personnel Status at the San'ao Nuclear Power Base. The CGN Engineering departments participating in this testing and verification included CGN Design Institute, the National Key Laboratory of Nuclear Power Safety Technology and Equipment (hereinafter referred to as the National Key Laboratory), CGN Engineering Cangnan Project Department, and Huasheng Technology. This joint test marks an important milestone in the project's transition from technology research and development to engineering application, providing key technical support for the quantitative analysis transformation of human factors safety management in China's nuclear power industry. The system, built upon the personnel fatigue status monitoring principle prototype developed under the Intelligent Nuclear Power strategic special project, has been iteratively improved with continuous support from the Yangjiang Chuangbao High-tech Research Project and the National Key Laboratory research projects, and has now evolved into a mature product suitable for engineering and large-scale application. Previously, relevant functional modules of the system had been deployed and data collected in applications such as human factors verification in the main control room of Yangjiang Nuclear Power Base and simulator training at Taishan Nuclear Power Base. The on-site testing and data collection at the San'ao Nuclear Power Base further verified the system's environmental adaptability and reliability across multiple nuclear power base scenarios, laying a solid foundation for subsequent industry-wide promotion and application.
2026-09-05

Qinshan Nuclear Power Completes Overhaul Validation of Grille Cleaning Robotic Arm
The grille cleaning robotic arm, an integrated system of UAV-based intelligent inspection and robotic arm automatic cleaning independently developed by the Mechanical Team of the Fourth Maintenance Division at Qinshan Nuclear Power, recently completed on-site validation during the Unit 2 312 overhaul at Qinshan Phase II. Designed for seawater system intake grille cleaning scenarios, this equipment transforms the original manual operation requiring entry into deep wells into an unmanned operation conducted under ground-based remote monitoring. The intake grille serves as a critical barrier for the cooling water system of a nuclear power plant, and its unobstructed condition is directly related to the stable operation of the unit. In traditional cleaning methods, workers were required to enter narrow shafts more than twenty meters underground to perform inspection and cleaning in confined spaces, which involved high labor intensity, low efficiency, and safety risks such as falls from height...
2026-09-03

Zhejiang Jinqimen Nuclear Power Unit 1 Pressurizer Relief Tank Successfully Hoisted into Place
On August 30, the pressurizer relief tank, a major nuclear island equipment item of Unit 1 at Zhejiang Jinqimen Nuclear Power Plant, contracted by China Nuclear Industry Fifth Construction Co., Ltd. (CNF), was successfully hoisted into place. The entire hoisting process was smooth and orderly, with overall safety and quality under control. This hoisting has laid a solid foundation for the subsequent installation of main nuclear island equipment and the construction of the primary loop system. The pressurizer relief tank is an important auxiliary equipment of the reactor coolant system in a nuclear power plant. Its main function is to collect and condense the high-temperature and high-pressure steam discharged from the pressurizer safety valves, ensuring the safe and stable operation of the reactor system. The relief tank hoisted this time is pre-installed equipment in the nuclear island. The main body of the equipment is heavy in weight and large in size, with limited hoisting workspace. After being hoisted into place, it needs to be placed in the nuclear island building for a long period, and subsequent construction will be constrained by space, making it necessary to introduce the equipment precisely within the civil construction window period.
2026-09-02

Qinshan Nuclear Power Plant Unit 2 Outage 218 Officially Commences
At 2:20 AM on September 1, Unit 2 of Qinshan Phase II was disconnected from the East China Power Grid, marking the official commencement of Outage 218. This outage is a Category C overhaul for Unit 2 of Qinshan Phase II. In addition to the routine annual overhaul items such as reactor coolant system head removal and installation, fuel handling, SG eddy current inspection and flushing, it also includes important special tasks such as generator rotor removal, insertion and inspection, diesel generator excitation system renovation, PSR weakness anti-boron dilution modification, reactor coolant system automatic makeup and residual heat removal eddy current detection function, and nuclear island low-voltage switchgear renovation. The planned items for this outage total 6,119: including 3,764 preventive items, 171 strategic maintenance items, 789 periodic tests, 133 modification work orders, and 1,262 other types of work.
2026-09-01

Qinshan Nuclear Power Membrane Deoxygenation Retrofit Project Put into Operation
Recently, the membrane deoxygenation retrofit project at Qinshan Nuclear Power completed commissioning and was put into operation. The project applies membrane deoxygenation technology to the auxiliary feedwater system (ASG) and reactor boron and water makeup system (REA) of Units 1 and 2 at Qinshan Nuclear Power Plant Phase II, optimizing and upgrading the original deoxygenation process. Units 1 and 2 of Qinshan Phase II originally adopted thermal deoxygenation. During long-term operation, this method presented issues such as insufficient redundancy in single-train equipment operation, high temperature and humidity on site, and potential exceedance of auxiliary feedwater tank temperature limits during summer peak temperature periods. To enhance system operational reliability, Qinshan Nuclear Power initiated relevant technical retrofits, introducing membrane separation packaged units to form a parallel standby configuration with the original thermal deoxygenation system, allowing flexible switching...
2026-08-28

Sichuan Huadu Nuclear Energy Wins Control Rod Drive Mechanism Orders for 4 Nuclear Power Units
On August 24, news came from Sichuan Huadu Nuclear Equipment Manufacturing Co., Ltd., located in Dujiangyan, Chengdu, Sichuan, that the company has won the orders for control rod drive mechanisms for 4 units among the first batch of nuclear power units approved for construction during the 15th Five-Year Plan period in China, with a total new contract value of 504 million yuan. The winning projects include Units 3 and 4 of Zhejiang Jinqimen Nuclear Power Plant, as well as Units 1 and 2 of Phase I of Liaoning Zhuanghe Nuclear Power. According to the previous approval arrangement by the State Council Executive Meeting, the new batch of nuclear power projects involves a total of 4 projects and 8 units, including Phase II of Zhejiang Jinqimen Nuclear Power, Phase III of Guangdong Taipingling Nuclear Power, Phase I of Liaoning Zhuanghe Nuclear Power, and Phase I of Shandong Laiyang Nuclear Power, all adopting China's self-developed third-generation nuclear power technology...
2026-08-27

Qinshan Nuclear Power Receives On-Site Visit for WANO Enhanced Performance Monitoring and Achieves Highest Rating
Recently, experts from the World Association of Nuclear Operators (WANO) Tokyo Center and Shanghai Office visited Qinshan Nuclear Power to conduct an on-site Enhanced Performance Monitoring (ePM) assessment for its nine units. Based on a comprehensive evaluation, the WANO on-site visit team unanimously concluded that Qinshan Nuclear Power has demonstrated steady overall performance improvement in recent years and currently operates at the industry's highest "benchmark" level, with expectations that performance across key areas will remain stable or continue to improve over the next six months. Additionally, WANO experts conducted follow-up evaluations on selected Areas for Improvement (AFIs) and Significant Operating Experience Report (SOER) recommendations arising from the 2025 WANO peer review of Qinshan Nuclear Power's nine units, deeming the overall results satisfactory. At a summary meeting held on August 20...
2026-08-22

Construction of the conventional island raft foundation slab for Unit 2 of Zhejiang Jinqimen Nuclear Power Plant completed
At 3:36 on August 20, the raft foundation slab pouring for the conventional island of Unit 2 at Zhejiang Jinqimen Nuclear Power Plant was successfully completed. With the final batch of concrete precisely placed into the formwork, the main structure construction of the conventional island for this unit was officially initiated. The concrete supply for this pouring operation was provided by CNNC Concrete Xiangshan Branch. The operation lasted 29 hours and 20 minutes, with a cumulative supply of over 4,000 cubic meters of concrete, achieving continuous and stable material delivery. The maximum pouring thickness at this section was 3 meters, with a height difference of 7 meters at the variable cross-section locations, and the structural design service life is 60 years. The project features large-volume, high-intensity construction characteristics, compounded by the rainy climate conditions on site, imposing stringent requirements on concrete supply continuity, delivery stability, and temperature control precision.
2026-08-21

First Concrete Pour Launched for Conventional Island of Jinqimen Nuclear Power Unit 2
At 22:16 on August 18, Zhejiang Jinqimen Nuclear Power construction reached another key milestone as the first concrete pour (FCD) for the raft foundation slab of the turbine generator building in the conventional island of Unit 2 was officially launched, marking the full commencement of the main construction of the conventional island of Jinqimen Nuclear Power Unit 2 and the project's official entry into the civil construction phase. The raft foundation slab being poured, as the core load-bearing structure of the conventional island, is a variable-cross-section, super-large-volume, waterproof and impermeable special concrete structure, and is the core section with the largest volume, most critical working conditions, and highest precision requirements among the conventional island raft foundation structures. This construction involves long continuous operation hours, stringent temperature control and crack prevention requirements, and significant construction organization challenges. To ensure the safe and high-quality completion of the project, CNNC Zheneng fully demonstrated the "owner" spirit, played the "backbone" role, and shouldered the "main force" responsibility, jointly establishing a dedicated technical task force with construction and supervision units, building on the mature FCD construction experience of Conventional Island Unit 1 to comprehensively optimize the raft construction process for Conventional Island Unit 2, strictly adhering to the highest quality standards and safety regulations for nuclear power construction.
2026-08-20

First PCS Heat Exchanger Pre-Introduction Successfully Completed at Zhejiang Jinqimen Nuclear Power Project
On August 16, the pre-introduction of the first PCS heat exchanger at the Zhejiang Jinqimen Nuclear Power Project, undertaken by China Nuclear Industry Fifth Construction Co., Ltd. (CNFC), was successfully completed. The entire introduction process was smooth and orderly, with safety and quality fully under control. The smooth pre-introduction of this PCS heat exchanger has laid a solid foundation for the subsequent modular dome lifting and overall project construction. As a core key equipment in the reactor building, the PCS heat exchanger features heavy weight, high installation precision, and significant difficulty. To ensure lifting safety, the project team organized 7 special discussions and 5 on-site surveys, sorted out preconditions, fabricated dedicated angle tooling, and clarified operation procedures and safety control points. During the lifting, management personnel provided full-time on-site supervision, with commanders and operators working in close coordination to strictly control equipment positioning. After 3 hours of continuous operation, a series of processes including equipment lifting, flipping to vertical, fine angle adjustment, and equipment pre-introduction were precisely completed, and the equipment was finally placed smoothly, marking the successful completion of the pre-introduction work.
2026-08-19

Module 4 of Steel Liner for Unit 3 of San'ao Nuclear Power Plant Successfully Hoisted
At 8:16 a.m. on August 15, the hoisting operation of Module 4 of the 3BRX steel liner for Unit 3 of the San'ao Nuclear Power Plant was officially launched. Under the stable operation of the 2,000-ton crawler crane of CNNC Machinery Engineering, the module successively completed a series of procedures including slewing, load-bearing travel, and alignment adjustment. After 220 minutes, the hoisting task was successfully completed. Module 4 of Unit 3 hoisted this time was integrally assembled from the fourth and fifth layers of the cylinder, with a diameter of approximately 45 meters and a height of 11.46 meters. The module features a large volume, susceptibility to deformation, and limited slewing space for the crane. The project team strictly implemented the special plan, completed site reinforcement, transport of baskets and counterweights, and crawler crane relocation in advance, organized hoisting simulation drills, and comprehensively inspected various safety hazards...
2026-08-18

Minister of Ecology and Environment Huang Runqiu Visits Zhejiang to Survey Ecological Environmental Protection and Nuclear Power Safety Regulation
From August 14 to 15, Minister of Ecology and Environment Huang Runqiu visited Lishui, Taizhou, and Ningbo in Zhejiang Province to survey ecological environmental protection efforts. During his tenure in Zhejiang, General Secretary Xi Jinping visited Lishui multiple times and expressed high expectations for strengthening ecological environmental protection. Huang Runqiu visited Liandu District in Lishui to inspect on-site the outcomes of Oujiang River ecological environment governance, rural living environment improvement, and ecological protection efforts, and also toured the Ecological Product Value Realization Mechanism (Lishui) Exhibition Hall to gain in-depth understanding of local practical experience in advancing ecological product value accounting and exploring the "Two Mountains" transformation pathway. He stated that it is essential to thoroughly study and implement Xi Jinping Thought on Ecological Civilization, firmly establish and practice the concept that lucid waters and lush mountains are invaluable assets, adhere to ecological priority and green development, and effectively protect this beautiful landscape. It is necessary to fully leverage the role of demonstration models, deepen the application of the "Thousand Villages Demonstration, Ten Thousand Villages Improvement" experience, continuously improve the rural living environment, develop distinctive industries such as "ecology + cultural tourism" tailored to local conditions, and support rural ecological revitalization. It is also important to summarize and promote the "Two Mountains" transformation model, actively expand channels for realizing ecological product value, and continuously convert ecological advantages into development advantages. Actively, safely, and in an orderly manner developing nuclear power is an important measure for building a clean, low-carbon, safe, and efficient energy system and for achieving carbon peak and carbon neutrality. Huang Runqiu visited the Sanmen Nuclear Power Plant in Taizhou, going deep into the main control room of the operating unit and the nuclear island building of the unit under construction to learn in detail about the operation status and construction progress of the nuclear power units, and to express condolences to and meet with the on-site supervision personnel of the East China Regional Office of Nuclear and Radiation Safety Supervision. He emphasized the need to uphold the rational, coordinated, and balanced nuclear safety philosophy, place the assurance of nuclear safety at the highest priority, strengthen whole-process supervision of nuclear power plants, and consolidate the primary responsibility for nuclear safety. It is necessary to urge enterprises to strictly implement the requirements of nuclear safety regulations and standards, effectively ensure the safe operation of nuclear power units and controlled construction quality, enhance equipment stability and reliability, strengthen radiation environment monitoring at nuclear power plants, and safeguard the high-quality development of the nuclear power industry with high-level safety. Ensuring the construction quality of nuclear power units is crucial to improving the safety level of nuclear power plants. Huang Runqiu visited the nuclear island foundation area of the Jinqimen Nuclear Power Plant in Ningbo to survey the construction progress and engaged in on-site exchanges with nuclear safety supervision personnel. He emphasized the need to implement the spirit of General Secretary Xi Jinping's important speeches and instructions on nuclear safety work, always adhere to the principles of safety first and quality first, effectively operate the nuclear safety responsibility system and quality management system, and continuously strengthen experience feedback and safety improvements. It is necessary to continuously advance the development of nuclear safety culture, strengthen bottom-line thinking and extreme-scenario thinking, enhance natural disaster monitoring, early warning, and preventive response, and effectively build premium and safe projects to strongly support the sustainable development of China's nuclear power industry and its "going global" strategy. Relevant officials from Zhejiang Province participated in the survey. Principal officials from relevant departments and bureaus of the Ministry of Ecology and Environment participated in the survey. Officials from the Department of Ecology and Environment of Zhejiang Province and others participated in the survey.
2026-08-17

Zhongyan Dadi Secures Consecutive Wins for Two Major Projects at a Nuclear Power Plant in Zhejiang
Recently, Beijing Zhongyan Dadi Technology Co., Ltd. (hereinafter referred to as "Zhongyan Dadi"), as a member of a consortium, has successfully won consecutive bids for the BOP sub-project construction works (Section 1) of Units 1 and 2 at a nuclear power plant in Zhejiang, as well as geotechnical-related projects for the waste treatment center sub-project. This successful bid represents a significant achievement in the company's continued deep engagement in national-level key nuclear power infrastructure, fully demonstrating Zhongyan Dadi's technical strength, mature performance capability, and core market competitiveness in nuclear power engineering construction. Planning renderings of the awarded projects The nuclear power plant in Zhejiang is a national key clean energy benchmark project, holding important strategic significance for optimizing the energy structure of the Yangtze River Delta region and advancing green, low-carbon transformation...
2026-08-04

Pre-Startup Review (PSUR) for Sanmen Nuclear Power Plant Unit 3 Completed
From July 15 to 30, the Pre-Startup Review (PSUR) for Sanmen Nuclear Power Plant Unit 3 was conducted at the Sanmen nuclear power plant site. The review was organized by the Shanghai Office of the World Association of Nuclear Operators (WANO), and the review team consisted of 21 experts from the WANO Shanghai Office, WANO Tokyo Center, and Korea Hydro & Nuclear Power Co., Ltd. Leaders of Sanmen Nuclear Power Company and personnel from relevant fields participated in this activity. The review aimed to systematically and comprehensively evaluate the readiness of Unit 3 prior to startup, identify areas for improvement, analyze causes, and propose improvement recommendations. Through site inspections, work observations, document package reviews, and personnel interviews, the WANO review team conducted a thorough assessment of...
2026-08-03

State Council Approves Four Nuclear Power Projects, Eight Units Granted Construction Approval
On July 31, the State Council's executive meeting reviewed and approved four nuclear power projects, including the Phase I project of Zhuanghe in Liaoning Province. The meeting noted that nuclear power units should be constructed and operated in accordance with the highest global safety standards, with strengthened safety oversight across the entire chain and all sectors, to ensure absolute nuclear safety. According to reports, the approved projects comprise a total of 8 units across 4 projects, specifically: 2 units for Phase II of CNNC's Jinqimen Nuclear Power in Zhejiang, 2 units for Phase I of Zhuanghe Nuclear Power in Liaoning, 2 units for Phase III of CGN's Taipingling Nuclear Power in Guangdong, and 2 units for Phase I of SPIC's Laiyang Nuclear Power in Shandong. According to the approvals previously issued by the National Nuclear Safety Administration for the Environmental Impact Reports (site selection stage) of the above four projects...
2026-07-31

China Energy Engineering Group Guangdong Thermal Power Engineering Co., Ltd. Wins Bid for CGNPC San'ao Nuclear Power Supporting 220 kV Transmission EPC Project
On July 28, China Energy Engineering Group Guangdong Thermal Power Engineering Co., Ltd. announced that it has recently won the bid for the EPC general contracting project of the 220 kV transmission line from Liulong Substation to Hengyang Substation under the CGNPC CS Project. This project is part of the nuclear power supporting infrastructure construction and an important component of the 220 kV construction and auxiliary power lines within the San'ao Nuclear Power Plant.
2026-07-29
Reading Ranking
- 1 Construction Site Leveling and Excavation Kicks Off for Hualong One Version 2.0 Demonstration Project of Zhejiang Jinqimen Nuclear Power Phase II
- 2 Qinshan Nuclear Power Receives On-Site Visit for WANO Enhanced Performance Monitoring and Achieves Highest Rating
- 3 Pre-Startup Review (PSUR) for Sanmen Nuclear Power Plant Unit 3 Completed
- 4 First Concrete Pour Launched for Conventional Island of Jinqimen Nuclear Power Unit 2
- 5 Qinshan Nuclear Power Plant Unit 2 Outage 218 Officially Commences
- 6 Qinshan Nuclear Power Completes Overhaul Validation of Grille Cleaning Robotic Arm
- 7 China Energy Engineering Group Guangdong Thermal Power Engineering Co., Ltd. Wins Bid for CGNPC San'ao Nuclear Power Supporting 220 kV Transmission EPC Project
- 8 State Council Approves Four Nuclear Power Projects, Eight Units Granted Construction Approval
- 9 Zhongyan Dadi Secures Consecutive Wins for Two Major Projects at a Nuclear Power Plant in Zhejiang
- 10 Minister of Ecology and Environment Huang Runqiu Visits Zhejiang to Survey Ecological Environmental Protection and Nuclear Power Safety Regulation
- 11 Module 4 of Steel Liner for Unit 3 of San'ao Nuclear Power Plant Successfully Hoisted
- 12 First PCS Heat Exchanger Pre-Introduction Successfully Completed at Zhejiang Jinqimen Nuclear Power Project
- 13 Construction of the conventional island raft foundation slab for Unit 2 of Zhejiang Jinqimen Nuclear Power Plant completed
- 14 Sichuan Huadu Nuclear Energy Wins Control Rod Drive Mechanism Orders for 4 Nuclear Power Units
- 15 Qinshan Nuclear Power Membrane Deoxygenation Retrofit Project Put into Operation