Hainan Changjiang Nuclear Power Unit 4 500kV Reverse Power Transmission Successfully Completed

Hainan Changjiang Nuclear Power Unit 4 500kV Reverse Power Transmission Successfully Completed

On August 19, 2026, the 500kV reverse power transmission of Unit 4 of the Hainan Changjiang Nuclear Power Phase II Project was successfully completed, marking another major milestone in the engineering construction of the unit. The 500kV reverse power transmission operation lasted approximately 15 hours. Throughout the power receiving process, equipment operated stably, all parameter indicators were excellent, protection devices acted accurately without error, and system live switching proceeded smoothly, fully achieving the established goal of successful power reception on the first attempt. The realization of this milestone fully verified that the design, manufacturing, and installation quality of the 500kV main switchyard, main transformers, high-voltage auxiliary transformers, and related auxiliary systems of Unit 4 all met the required standards. The Hainan Project Department of CNNC Engineering coordinated design, procurement, construction,...

2026-08-21

Huaneng Hainan Changjiang Nuclear Power Plant Unit 4 Secondary Loop Combined Hydrostatic Test Successfully Completed

Huaneng Hainan Changjiang Nuclear Power Plant Unit 4 Secondary Loop Combined Hydrostatic Test Successfully Completed

At 04:29 on August 6, 2026, witnessed jointly by Huaneng Changjiang Nuclear Power Company and all participating construction units, the secondary loop combined hydrostatic test of Unit 4 was completed, laying a solid critical prerequisite foundation for the comprehensive implementation of subsequent cold functional tests of the unit. Hydrostatic test curve diagram The secondary loop hydrostatic test is the core critical test following the blasting purging process in the unit's secondary loop system, and constitutes a mandatory acceptance procedure during the construction and installation phase of the Hualong One nuclear power unit. The test primarily targets the steam generator secondary side system, main steam pipelines, feedwater system, auxiliary valves, supports and hangers, and all associated piping, comprehensively verifying the overall structural pressure resistance, weld and flange sealing performance, and...

2026-08-07

The steam-blowing operation for the secondary-circuit main steam piping of Hainan Changjiang Nuclear Power Unit 4 has been successfully completed.

The steam-blowing operation for the secondary-circuit main steam piping of Hainan Changjiang Nuclear Power Unit 4 has been successfully completed.

On July 23, the "shock blow" cleaning operation for the secondary-circuit main steam piping of Unit 4 at the Hainan Changjiang Nuclear Power Plant—undertaken by China Nuclear Industry Fifth Construction Co., Ltd.—was successfully completed. The

2026-07-27