Unit 2 of Kola NPP begins 30-day scheduled preventive maintenance
On August 2, 2026, Unit 2 of the Kola Nuclear Power Plant launched scheduled preventive maintenance (SPM) incorporating modernization elements, expected to last approximately 30 days. During this mid-cycle overhaul, specialists will carry out extensive work on critical equipment. In the reactor shop, major repairs will be performed on part of the steam generators, main circulation pumps, and primary circuit piping. Plans also include disassembly and reassembly of the reactor plant, nuclear fuel replacement, and repair of the reactor internals and safety system equipment. In the turbine shop, turbine units, turbogenerators, circulation pumps, low-pressure heaters, and separators-superheaters will be repaired. On the electrical side, transformers and diesel generators will undergo maintenance. Additionally, upgrades are planned for the automatic chemical control system of the primary coolant and the DC power distribution panels for the entire station and individual units.