Russia's Seversk launches core basket assembly for lead-cooled fast reactor
Recently, in the closed administrative-territorial formation of Seversk in Tomsk Oblast, Russia, the expanded assembly of the reactor core basket has officially begun at the construction site of the innovative "BREST-OD-300" (BREST-OD-300) power unit. The "BREST-OD-300" power unit, with an installed capacity of 300 MW and employing a fast neutron reactor, is the world's first power reactor using lead as coolant, and is currently being built within the site of the Siberian Chemical Combine (АО «СХК», part of the fuel division of the State Atomic Energy Corporation Rosatom) as a component of the fourth-generation Experimental Demonstration Energy Complex (ОДЭК), under the industry strategic project "Proryv" (Breakthrough).

The core basket is used to reliably hold fuel assemblies containing nuclear fuel in strictly specified positions, while forming and guiding the flow of the liquid metal lead coolant. The metal structure has a total weight of 160 tonnes and consists of five large components, all manufactured by Atommash, part of the mechanical engineering division of the State Atomic Energy Corporation Rosatom, located in Rostov Oblast.
Ivan Babich, a representative of the management of the Experimental Demonstration Energy Complex of the Siberian Chemical Combine, stated that the core basket assembly is a fundamentally new stage of work compared with the construction of the reactor pressure vessel, and that the team is building the "heart" of the BREST-OD-300 reactor facility, which determines its reliability and efficiency for decades to come. After the expanded assembly of the large components is completed, the structure will be moved into the reactor pressure vessel and installed in its design position within the metal shell of the central cavity, after which the final stage of expanded assembly will be completed on site, including the installation of the last large component — the inner shell.
While the assembly of the reactor facility equipment is progressing, construction of the foundation for the turbine generator set continues at the site, along with preparations for the installation of the turbine of the BREST-OD-300 power unit. It is noted that the "Proryv" project is an industry strategic project of the State Atomic Energy Corporation Rosatom, aimed at establishing a new technological platform for nuclear energy based on fast neutron reactors with a closed nuclear fuel cycle, thereby eliminating the need for evacuation and resettlement of residents in the event of severe accidents at nuclear power plants, and generating electricity and repeatedly reusing spent nuclear fuel without accumulating irradiated nuclear fuel, thus removing the limitation of a constrained resource base for nuclear energy; the Experimental Demonstration Energy Complex at the site of the Siberian Chemical Combine in Seversk will validate the relevant technologies, demonstrate the closure of the nuclear fuel cycle, and take the first step toward building a new generation of nuclear energy.
Disclaimer: Information republished from partner media, institutions or other websites is provided for reference and communication purposes only. It does not imply endorsement of its views or verification of its accuracy. Please contact us if any content infringes rights or requires correction.