CNNC Fifth Construction Company Completes Ring Rail Assembly for Jinqimen Unit 1
Recently, the ground assembly of the ring support girder and ring rail for Unit 1 of the Jinqimen Nuclear Power project in Zhejiang Province, undertaken by China Nuclear Industry 5th Construction Co., Ltd., was successfully completed. This ground assembly has laid a solid foundation for the subsequent integral hoisting of the polar crane for the unit. As the key structures for the operation and load-bearing of the polar crane, the ground assembly precision and structural quality of the ring support girder and ring rail are directly related to the stability of the subsequent high-altitude integral hoisting and the construction pace during the nuclear island installation phase. The project team therefore designated the ground assembly as a key phased...
2026-11-20
Nuclear Safety Inspection Conducted on Preparation for FCD of Unit 4 of Sanao Nuclear Power Plant
Recently, the East China Nuclear and Radiation Safety Supervision Station of the Ministry of Ecology and Environment (hereinafter referred to as the East China Supervision Station) organized a nuclear safety inspection on the preparation for the first concrete pouring (FCD) of the nuclear island foundation of Unit 4 of the Zhejiang Sanao Nuclear Power Plant. FCD is a key milestone in nuclear power project construction, marking the official start of main construction. The East China Supervision Station attached great importance to this inspection and made careful preparations in the preparatory stage, inviting technical support organizations and senior experts in the industry to form an inspection team covering specialties such as geology, civil engineering, and quality assurance, and developed a targeted inspection plan based on key and difficult issues in recent regulatory work. During the inspection, the inspection team carried out, in accordance with the inspection plan, document reviews and personnel interviews covering all areas, inspected the preparation of construction management conditions, the preparation of technical conditions, the operation of the quality assurance system, the handling of outstanding issues from previous construction supervision inspections, and the establishment and operation of the experience feedback system, verified the progress in implementing nuclear safety review commitments, and conducted on-site inspections of key areas such as the raft foundation of the reactor building, raw material storage sites, the concrete laboratory, and the concrete batching plant. Based on the inspection results, the East China Supervision Station put forward nuclear safety management requirements in accordance with the law, specified rectification deadlines, and urged the operating organization to fulfill its primary responsibility for nuclear safety, strictly implement rectification requirements, and ensure the construction quality of the nuclear power project.
2026-11-13
Unit 2 of Sanao Nuclear Power Plant Completes First Fuel Load
Recently, China General Nuclear Power Group (CGN) announced that Unit 2 of the Sanao Nuclear Power Plant, located in Cangnan, Wenzhou, Zhejiang Province, has successfully completed the loading of fuel assemblies into the reactor core, marking the unit's official entry into a new phase of commissioning and preparation for operation with nuclear fuel, and representing a key step toward full construction and commercial operation. As the second of six Hualong One (HPR1000) third-generation nuclear power units planned for the Sanao site, Unit 2 officially poured its first batch of concrete in late December 2021. Prior to this, the unit had successively completed cold functional tests and hot functional tests, comprehensively verifying the equipment performance of the reactor system under severe temperature and pressure conditions...
2026-11-12
First Concrete Poured for Unit 4 of Zhejiang Sanao NPP: How Can a Single Site Balance Construction, Commissioning and Operation?
When Unit 4 broke ground, Unit 1 was already supplying power to the grid. At 8:28 on November 10, first concrete was poured for the nuclear island of Unit 4 at the Sanao nuclear power project in Cangnan, Zhejiang, marking the start of main construction. At the same site, Unit 1 entered commercial operation on April 29, Unit 2 has completed its first fuel load, and Unit 3 began main construction of its nuclear island in December 2025. The four Hualong One units are respectively in operation, startup preparation and construction. For site managers, Sanao now has to deal with two types of issues simultaneously: how to pass on the construction experience of identical units to the next one, and how to protect systems already in operation or under commissioning from interference by adjacent construction.
2026-11-11
Unit 4 of CGN's Zhejiang Sanao Nuclear Power Project officially commences construction
Recently, the first concrete pouring for the nuclear island of Unit 4 of the Sanao Nuclear Power Project in Wenzhou, Zhejiang Province officially began, marking the full commencement of the unit's main works and the official entry of the project's Phase II into the stage of large-scale construction. As the first Hualong One project in the Yangtze River Delta region and the country's first nuclear power project to introduce private capital participation, the continued advancement of the Sanao Nuclear Power Project has set an important example for the high-quality development of clean energy in China. Located in Wenzhou, Zhejiang Province, the Sanao Nuclear Power Project is the first Hualong One project in the Yangtze River Delta region and the country's first nuclear power project to introduce private capital participation. Unit 4, which commenced construction this time, is part of Phase II of the Sanao Nuclear Power Project and is China General Nuclear Power Group...
2026-11-11
CNNC Mechanical Engineering Wins Bid for Jinqimen Nuclear Power Phase II Hoisting
Recently, CNNC Mechanical Engineering Co., Ltd. officially announced that it had successfully won the bid for the heavy-lift hoisting engineering project of Zhejiang Jinqimen Nuclear Power Phase II (Units 3 and 4). As another core project undertaken by the company at Jinqimen Nuclear Power following the heavy-lift hoisting engineering for Units 1 and 2, this project is the first approved nuclear power project in Zhejiang Province during the 15th Five-Year Plan period. Once fully completed, it will provide strong support for energy and electricity supply security and green, low-carbon transformation in Zhejiang Province and the Yangtze River Delta region. Zhejiang Jinqimen Nuclear Power Phase II fully adopts the Hualong One Version 2.0 pressurized water reactor nuclear power units and is among the first batch of demonstration projects for this advanced reactor type. With the continuous iterative upgrading of nuclear power technology, hoisting modules...
2026-11-07
Unit 2 of Phase I of the Sanao Nuclear Power Project Completes First Fuel Loading
Recently, Unit 2 of Phase I of CGN's Zhejiang Sanao Nuclear Power Project successfully completed its first nuclear fuel loading, marking the unit's official transition from the engineering installation phase to the new stage of commissioning with nuclear fuel in the main systems, and representing a key step toward the full completion and commercial operation of Phase I. It is reported that the fuel loading operation adopted a semi-automatic refueling system, precisely transferring 177 nuclear fuel assemblies sequentially into the reactor core. Since the commencement of nuclear island installation, the Sanao project department of China Nuclear Industry 23 Construction Co., Ltd., the contractor, has strictly followed the principles of "safety first, quality first, pursuit of excellence," and completed a series of major prerequisite tests—including nuclear circuit flushing and cold and hot performance tests—to a high standard...
2026-11-03
Zhejiang Ziming Cryogenics Secures Investment from Two Major Central Energy SOEs to Scale Up Fusion Cryogenic Systems
Recently, Zhejiang Ziming Cryogenics Technology Co., Ltd. announced the completion of a new round of financing. This round brought together multiple institutions including the CNNC Science and Technology Innovation Fund under China National Nuclear Corporation and the Oriental Zhongying High-end Energy Equipment Fund managed by Dongfang Electric Group in partnership with Bank of China Asset Management, marking the capital market's strong recognition of the company's breakthroughs in bottleneck cryogenic technologies and engineering applications. Founded in 2022, Ziming Cryogenics has long been dedicated to the research and development of ultra-low temperature technologies and core equipment, specializing in complete cryogenic system solutions, high-capacity Stirling cryocoolers, ultra-low temperature precision control valves, and cryogenic pumps and fans. Currently, its kilowatt-class Stirling cryocoolers, covering...
2026-10-21
Fangjiashan Nuclear Power Unit 109 Overhaul Successfully Concluded, Technology Empowers a Solid Safety Foundation
Recently, the Fangjiashan Nuclear Power Unit 109 overhaul was successfully concluded. During this overhaul, the maintenance project team of China Nuclear Industry 22nd Construction Co., Ltd. cumulatively executed 173 work orders (including 34 high-risk work orders), simultaneously covering two major areas—civil maintenance and pipeline anti-corrosion—spanning the National Day holiday, and fully ensuring the steady progress of all tasks with a professional team, laying a solid foundation for the safe operation of the plant. It is understood that civil maintenance and pipeline anti-corrosion, as important invisible defense lines for ensuring the integrity of structures, are the fundamental guarantee for the safe operation of the unit. In this overhaul, the confined space operation of the underwater culvert of the PX pump house and the anti-corrosion lining repair of the ATE wastewater neutralization tank were key high-risk concealed works. Facing...
2026-10-20
Sanmen Nuclear Power's Multiple Management Innovation Achievements Recognized, Supporting High-Quality Development of Nuclear Power
Recently, Sanmen Nuclear Power proudly received multiple management innovation achievement awards. Among them, "Construction and Efficiency Enhancement of a Data-Driven Nuclear Power Thermal Performance Supervision System" won the Second Prize of CNNC, and "Data-Driven Predictive Maintenance Management for Nuclear Power Enterprises" won the Third Prize. In addition, "Full Life-Cycle Health Management of Equipment Based on Multi-Source Data and System Collaboration for Nuclear Power Enterprises" and "Construction of a Reliability-Centered Full-Process Quality Supervision System for Nuclear Fuel Manufacturing" also won the Third Prize of China Nuclear Power Management Innovation. These achievements fully demonstrate Sanmen Nuclear Power's innovation strength in relying on digital transformation, deepening nuclear power operations, and improving quality and efficiency, injecting strong momentum into the year-end sprint...
2026-10-16
Preparations Underway for First Nuclear Fuel Loading at San'ao Nuclear Power Project Unit 2
On October 7, it was learned from CGN Cangnan Nuclear Power Co., Ltd. that San'ao Nuclear Power Project Unit 2 is carrying out preparatory work before its first nuclear fuel loading. Once fuel loading is completed, the unit will enter the stage of nuclear commissioning of the primary system with nuclear fuel. During the National Day holiday, personnel at key positions of the San'ao Nuclear Power Project stayed at the front line to fully advance the pre-loading preparations. A relevant person in charge of the Fuel Management Section of the Technical Support Department of CGN Cangnan Nuclear Power Co., Ltd. stated that in order to ensure the high-quality completion of Unit 2's first fuel loading and core photography operations, the project working group strictly implemented relevant regulations and management requirements for nuclear material control, and coordinated the advancement of various pre-loading tasks including the submission of first loading information and the approval request for fuel assembly transfer.
2026-10-08
First Backup Emergency Diesel Generator of Hualong One Officially Available at Sanao Nuclear Power Unit 2
On October 2, the first backup emergency diesel generator (9LHW) of Hualong One completed the replacement grid connection test at Sanao Nuclear Power Unit 2 and was officially put into service. The equipment can replace any one of the original 12 emergency diesel generators (EDGs) in Phase I and Phase II projects, significantly improving the redundancy, reliability, and maintenance flexibility of the plant's emergency power supply. Sanao Nuclear Power Phase I and Phase II each have 3 emergency busbars, with one EDG configured for each busbar. However, due to the absence of cross-power supply for loads, the preventive maintenance windows of the original units were concentrated, affecting the overhaul schedule. Since 2021, Cangnan Nuclear Power has promoted the project of adding backup diesel generators, improving from the design source, building a new backup emergency diesel generator building (BDD), and constructing corridors and cables connected to each unit...
2026-10-03
CGN Cangnan No. 3 Nuclear Power Co., Ltd. Established
According to Qichacha APP, CGN Cangnan No. 3 Nuclear Power Co., Ltd. was recently established, with its business scope including: heat production and supply; technology import and export; goods import and export, etc. Qichacha equity penetration shows that the company is jointly held by China General Nuclear Power Corporation, Zhejiang Zheneng Electric Power Co., Ltd., and Zhejiang Geely Industrial Investment Holding Co., Ltd., a wholly-owned subsidiary of Zhejiang Geely Holding Group Co., Ltd., among others.
2026-10-03
CGN Environmental Protection and Cangnan Nuclear Power Sign a New Round of General Contracting Agreement for Nuclear Environmental Protection Business
Recently, CGN Environmental Protection and Cangnan Nuclear Power officially signed a new round of general contracting agreement for nuclear environmental protection business. This marks a comprehensive upgrade of their cooperation from version 1.0 to version 2.0, and also a substantive implementation of the Group's deepening reform strategy in the field of nuclear environmental protection. Zhan Weihua, Deputy Party Secretary and General Manager of Cangnan Nuclear Power, and Qin Geng, Party Committee Member and Chief Accountant; Ren Junhua, Deputy Party Secretary and General Manager of CGN Environmental Protection, Lu Shubao, Party Committee Member and Deputy General Manager, and Yang Wei, Party Committee Member and Deputy General Manager attended the signing ceremony. In 2025, CGN Environmental Protection transitioned toward nuclear environmental protection business and signed the first round of general contracting agreements with multiple plants. Over the past year, the company has continuously honed its capabilities in business undertaking and execution, and is accelerating the construction of an integrated...
2026-10-02
Construction of BOP Sub-item Installation Works for Units 1 and 2 of Zhejiang Jinqimen Nuclear Power Plant Officially Commences
On September 29, the BOP sub-item installation works (Lot 1 and Lot 2) for Units 1 and 2 of Zhejiang Jinqimen Nuclear Power Plant, contracted by Beijing Zhongyan Dadi Technology Co., Ltd. (hereinafter referred to as Zhongyan Dadi), officially commenced, marking the full launch of the project construction. Jinqimen Nuclear Power Plant is located in Xiangshan County, Ningbo City, Zhejiang Province. It is a benchmark clean energy project under national key planning. Once fully completed, its annual power generation capacity will reach 55 billion kWh, which is of great strategic significance to the optimization of the energy structure and green low-carbon transformation in the Yangtze River Delta region. The BOP (nuclear power plant supporting facilities) sub-item is an important foundation for ensuring the safe and stable operation of nuclear power units, and its construction precision and quality control standards are far...
2026-09-30