Fangchenggang Nuclear Power Phase I Marks 10th Anniversary of Commercial Operation: Two Units Have Cumulatively Supplied Over 160 Billion kWh, with WANO Indicators Achieving Full Marks for Seven Consecutive Years

Fangchenggang Nuclear Power Phase I Marks 10th Anniversary of Commercial Operation: Two Units Have Cumulatively Supplied Over 160 Billion kWh, with WANO Indicators Achieving Full Marks for Seven Consecutive Years

Recently, Phase I of the Fangchenggang Nuclear Power Plant under China General Nuclear Power Group officially ushered in the 10th anniversary of its commercial operation. As the first nuclear power project in western China and in an ethnic minority region, the two million-kilowatt-class pressurized water reactor units at the site have maintained safe and stable operation for ten years since being put into operation. Their WANO composite index has achieved full marks for seven consecutive years, and they have cumulatively delivered over 160 billion kWh of clean electricity to the Beibu Gulf Economic Zone. It is understood that Phase I of the Fangchenggang Nuclear Power Project is located on Qisha Peninsula in Fangchenggang City, Guangxi Zhuang Autonomous Region, and is an important energy backbone project of the national Western Development Strategy. The project planned to build two self-developed CPR1000 pressurized water reactor nuclear power units with a single-unit capacity of 1.08 million kilowatts...

2026-10-04

Guangxi Nuclear Power Holds the 2026 Third-Quarter Nuclear Safety Culture Promotion Studio Joint Exchange Activity

Guangxi Nuclear Power Holds the 2026 Third-Quarter Nuclear Safety Culture Promotion Studio Joint Exchange Activity

To cultivate a solid foundation for nuclear safety culture and promote the exchange and sharing of technical experience among regulatory authorities, owners, and all participating construction parties, the 2026 third-quarter Nuclear Safety Culture Promotion Studio joint exchange activity for the South China Nuclear and Radiation Safety Supervision Station of the Ministry of Ecology and Environment (hereinafter referred to as the "South China Supervision Station"), the Bailong Nuclear Power Project, and the Fangchenggang Nuclear Power Project was recently held at Guangxi Nuclear Power. The activity was chaired by Zheng Tao, head of the on-site supervision group for the Bailong Nuclear Power Project of the South China Supervision Station. Chen Rongda, director of the Third Nuclear Facility Supervision Division of the South China Supervision Station, Li Qiang, general manager of Guangxi Nuclear Power, and Hou Yousheng, general manager of Fangchenggang Nuclear Power, attended the activity, along with representatives from all participating construction units. All parties gathered together to focus on the cultivation and implementation of nuclear safety culture...

2026-09-30

South China Regional Office Conducts Special Nuclear Safety Inspection on Fangchenggang Nuclear Power Plant in Response to Extreme Weather

South China Regional Office Conducts Special Nuclear Safety Inspection on Fangchenggang Nuclear Power Plant in Response to Extreme Weather

Since 2026, the coastal area where Fangchenggang City, Guangxi Zhuang Autonomous Region, is located has experienced frequent extreme weather events. During the passage of Typhoon Maysak in July, the maximum gust measured on site at the Fangchenggang Nuclear Power Plant reached Force 9, with cumulative rainfall during the event reaching as high as 424.2 mm; in August, affected by the peripheral circulation of Typhoon Zitan, the area once again suffered sustained heavy wind and rain, with localized cumulative rainfall exceeding 300 mm. In response to the severe climatic situation of superimposed strong typhoons and short-duration heavy rainfall, the South China Regional Office of Nuclear and Radiation Safety Inspection of the Ministry of Ecology and Environment (hereinafter referred to as the South China Regional Office) recently took the initiative to...

2026-09-27

Concrete Placement Completed for Raft Foundation of Circulating Water Pit on North Side of 5BMX Turbine Generator Building at Fangchenggang Nuclear Power Plant

Concrete Placement Completed for Raft Foundation of Circulating Water Pit on North Side of 5BMX Turbine Generator Building at Fangchenggang Nuclear Power Plant

On August 30, the concrete placement for the raft foundation of the circulating water pit on the north side of the 5BMX turbine generator building at the Fangchenggang Nuclear Power Plant in Guangxi, undertaken by China Energy Engineering Group Anhui Electric Power Construction No.2 Engineering Co., Ltd., was completed. The total concrete volume placed was 796 cubic meters, with two truck-mounted concrete pumps operating simultaneously, and the work was completed in approximately 22 hours. The circulating water pit raft foundation is a key underground structure of the turbine hall. This mass concrete placement was carried out using the horizontal layered pouring method. The project department made advanced overall arrangements, refined the construction plan, and organized safety and technical briefings for construction. During the placement, project personnel performed their respective duties with coordinated collaboration, efficiently advancing concrete transport, placement, vibration, surface finishing, curing, and other tasks. Dedicated personnel were assigned for on-site supervision to strictly control key parameters such as pouring speed, vibration depth, and slump, and to rigorously implement safety and quality control measures, ensuring the entire construction process was safe, controllable, and quality-compliant. Ultimately, this critical civil construction milestone was successfully completed, laying a solid foundation for the subsequent circulating water system construction and the overall structural construction of the turbine hall.

2026-09-02

Fangchenggang Nuclear Power Holds Special Symposium on Nuclear Safety Management

Fangchenggang Nuclear Power Holds Special Symposium on Nuclear Safety Management

Recently, Gao Zhigang, Secretary of the Party Committee and Chairman of Fangchenggang Nuclear Power, presided over a special symposium centered on the theme of "firmly holding the nuclear safety 'rice bowl' in our own hands," engaging in exchanges with departments including Operations Division I, Operations Division II, Nuclear Safety and Licensing Department, and Training Department, while also delivering relay training in accordance with the requirements of CGN's 2026 "Red Egret - Party Committee Member Plan" training program. At the symposium, department representatives shared work insights and best practices based on their job responsibilities and frontline work realities, focusing on role positioning, capability enhancement, value creation, and cognitive upgrading, while also offering suggestions on production safety management, risk prevention and control, and on-site execution. Gao Zhigang...

2026-09-01

Fangchenggang Nuclear Power Station Unit 2 Completes First Ten-Year Overhaul

Fangchenggang Nuclear Power Station Unit 2 Completes First Ten-Year Overhaul

On the morning of August 25, Unit 2 of CGNPC Fangchenggang Nuclear Power Station successfully synchronized to the grid on its first attempt following the 7th overhaul, marking the completion of the F207 overhaul undertaken by CGNPC Service Maintenance Company. This overhaul was the first ten-year overhaul since Unit 2 was put into commercial operation. The maintenance process achieved the goal of "no indicator events in safety, quality, and schedule," and made breakthroughs in charging pump maintenance and nuclear-grade socket welding operations. During this overhaul, the nuclear-grade socket welding project was implemented on-site for the first time. To ensure work quality, the maintenance team completed preparatory work in advance, including welding procedure qualification certification, skill qualification process card review and submission, test piece welding, and non-destructive testing, all of which passed acceptance.

2026-08-28

Supervision and assessment of the comprehensive on-site exercise at Fangchenggang Nuclear Power Plant successfully completed.